Bravo Zulu has the following cost and production data for the Blending Department for December 2016 Cost data: Beginning work in process inventory, December 1 $50,000 $26,000 $76,000 Direct Materials Conversion Cost Cost incurred during production in December Direct Materials Conversion costs Total costs $430,000 $136,000 $566,000 Production data Completed ad transferred out 52,000 Ending work in process 8,000 Ending work in process was 100% complete as to materials and 25% complete as to conversion costs. Instructions (a) Determine the unit cost for materials. (b) Determine the unit cost for conversion.Explanation / Answer
a Unit cost for materials = (50000+430000)/(52000+8000)= 8 b Unit cost for conversion = (26000+136000)/(52000+8000*25%)= 3