Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

The Cengage Company makes Elmo toys. It has developed the following per unit sta

ID: 2600151 • Letter: T

Question

The Cengage Company makes Elmo toys. It has developed the following per   unit standard costs for 2017 for each item:

                                  Direct         Direct    Manufacturing

                                 Materials        Labor       Overhead

                          

     Standard Quantity           4 pounds         3 hours      3 hours

     Standard Price               $3.00/lb         $8.00/hr     $4.00/DLH

     Unit Standard Cost           $12.00          $24.00        $12.00

    

     In 2017, the company expected to produce 20,000 units of toys and

    planned a level of 60,000 hours of direct labor.

    

     Actual results for 2017 are presented below:

     1. Direct materials purchased and used were 84,000 pounds at a cost of

        $231,000.

     2. Direct labor costs were $512,400 for 61,000 direct labor hours

        actually worked.

     3. Actual manufacturing overhead was $238,000.

     4. Actual production was 20,500 units.

    

     INSTRUCTIONS

     Compute the following variances:

         1. Direct materials: total, price and quantity.

         2. Direct labor: total, price and quantity

         3. Total overhead variance.

Place answer Show calculations here here (1) Total materials variance: Materials price variance: Materials quantity variance: (2) Total labor variance: Labor price variance: Labor quantity variance: (3) total overhead variance

Explanation / Answer

Cengage Company Production 20500 Units Expected Production 20000 Units Direct Material Direct Labor Manufacturing Overhead Standard Quantity 4 Pounds 3 Hours 3 Hours Standard Price $3 lb $8 hours $4 hours Unit Standard cost $12 $24 $12 Direct Material Purchase Price 84000 Pounds   $231,000 Direct Labour 61000 DLH 512400 Actual Manufacturing Overhead 238000 Actual Material Price Per Pound=($231000/84000) $                   2.75 Actual Labor cost per hours=($512400/61000) 8.4 Actual Manufacturing Overhead Per hours=($238000/61000) 3.90 1) Direct material price variance Actual Material used( Standard Price-Actual Price) Direct material price variance=84000*($3-$2.75)= $         21,000.00 (F) Direct material Quantity variance=((4*20500)-84000))*$3 (Standard Quantity-Actual Quantity)standard Price $         (6,000.00) (U) Total material cost Variance=($21000-$6000) Direct material Price variance+ Direct material Quantity variance $         15,000.00 (F) 2) Direct labour rate variance=61000*($8-$8.4) Actual hours(Standard rate-Actual Rate) $      (24,400.00) (U) Direct Labour efficiency variance=((3*20500)-61000)*$8 (Standard Hours-Actual Hours)*Standard Rate $           4,000.00 (F) Total direct labour cost variance=(-$24400+$4000) Direct labour rate variance+ Direct labour efficiency variance $      (20,400.00) (U) 3) Total Overhead Variance= Actual Overhead-Overhead applied Applied Overhead=(Standard Hours*Standard rate) Standard Hours=Budgeted Production*hours required per units of prod Standard Hours=20000*3=60000 Applied Overhead=(60000*$4)= 240000 Total Overhead Variance=($238000-$240000)= $         (2,000.00) (U)