Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Part 3- Problem: (15 points) The ledger of Hsu Company has the following work in

ID: 2600394 • Letter: P

Question

Part 3- Problem: (15 points) The ledger of Hsu Company has the following work in process account. WORK IN PROCESS-PAINTING 5/31 Transferred out 5/1 Balance 5/31 Labor 5/31 Balance 8,741 5/31 Materials 6,460 2,400 5/31 Overhead1626 Production records show that there were 500 units in the beginning inventory, 30% complete, 1,350 units started, and 1,350 units transferred out. The beginning work in process had materials cost of $4,862 and conversion costs of $3,879. The units in ending inventory were 40% complete. Materials are entered at the beginning of the painting process Instructions (a) How many units are in process at May 31? (b) What is the unit materials cost for May? (c) What is the unit conversion cost for May? (d) What is the total cost of units transferred out in May? (e) What is the cost of the May 31 inventory?

Explanation / Answer

Answer:

(a) How many units are in process at May 31?

Work in process May .1

           500

Started into production

       1,350

Total units to be accounted for

1,850

Less: Transferred out

(1,350)

Work in process, May 31

500

(b) What is the unit materials cost for May?

Units

Units transferred out

1,350

Work in process, May 31

    500

1,850

Cost ($)

Work in process, May 1

   4,862

Costs added:

Material

     6,460

Total Cost

  11,322

Unit Material Cost

$ 6.12

(c) What is the unit conversion cost for May?

Units

Units transferred out

1,350

Work in process, May 31

200

(500 X 40%)

Total

1,550

Work in process, May 1

Cost $    3,879

Costs added:

Labor

    2,400

Overhead

    1,626

Total Cost

    7,905

Unit Conversion Cost

      $5.10

(d) What is the total cost of units transferred out in May?

Material ( 1,350 X 6.12)

$ 8,262

Conversion Cost (1,350 X 5.10)

$6,885

Total Cost of transferred out

$15,147

(e) What is the cost of the May 31 inventory?

Material ( 500 X 6.12)

$3,060

Conversion Cost (200X 5.10)

$1,020

Total Cost of May 31 inventory

$4,080

Answer:

(a) How many units are in process at May 31?

Work in process May .1

           500

Started into production

       1,350

Total units to be accounted for

1,850

Less: Transferred out

(1,350)

Work in process, May 31

500

(b) What is the unit materials cost for May?

Units

Units transferred out

1,350

Work in process, May 31

    500

Total

1,850

Cost ($)

Work in process, May 1

   4,862

Costs added:

Material

     6,460

Total Cost

  11,322

Unit Material Cost

$ 6.12

($11322/1850)

(c) What is the unit conversion cost for May?

Units

Units transferred out

1,350

Work in process, May 31

200

(500 X 40%)

Total

1,550

Work in process, May 1

Cost $    3,879

Costs added:

Labor

    2,400

Overhead

    1,626

Total Cost

    7,905

Unit Conversion Cost

      $5.10

($ 7905/1550)

(d) What is the total cost of units transferred out in May?

Material ( 1,350 X 6.12)

$ 8,262

Conversion Cost (1,350 X 5.10)

$6,885

Total Cost of transferred out

$15,147

(e) What is the cost of the May 31 inventory?

Material ( 500 X 6.12)

$3,060

Conversion Cost (200X 5.10)

$1,020

Total Cost of May 31 inventory

$4,080