Consider the following two mutually exclusive projects: Year Cash Flow (X) Cash

ID: 2631015 • Letter: C

Question

Consider the following two mutually exclusive projects: Year Cash Flow (X) Cash Flow (Y) 0 :$16,200 1 6,680 7,230 2 7,260 7,760 3 4,780 3,570

Requirement 1: (a) What is the IRR of Project X? (Do not round intermediate calculations. Enter your answer as a percentage rounded to 2 decimal places (e.g., 32.16).) IRR %

(b) What is the IRR of Project Y? (Do not round intermediate calculations. Enter your answer as a percentage rounded to 2 decimal places (e.g., 32.16).) IRR %

Requirement 2: What is the crossover rate for these two projects? (Do not round intermediate calculations. Enter your answer as a percentage rounded to 2 decimal places (e.g., 32.16).)

Explanation / Answer

a)

0 = -16200 + 6680/(1+IRR) + 7260/(1+IRR)^2 + 4780/(1+IRR)^3

IRR = 8.01%


b)
0 = -16200 + 7230/(1+IRR) + 7760/(1+IRR)^2 + 3570/(1+IRR)^3

IRR = 7.93%


requirement 2:

let C be cross over rate


6680/(1+C) + 7260/(1+C)^2 + 4780/(1+C)^3 = 7230/(1+C) + 7760/(1+C)^2 + 3570/(1+C)^3


C = 9.68% ...ans