Question
Cadavieco Detailing's cost formula for its materials and supplies is $2,030 per month plus $8 per vehicle. For the month of November, the company planned for activity of 98 vehicles, but the actual level of activity was 58 vehicles. The actual materials and supplies for the month was $2,760.
The materials and supplies in the planning budget for November would be closest to:
$2,814
$2,494
$2,760
$4,405
Cadavieco Detailing's cost formula for its materials and supplies is $2,030 per month plus $8 per vehicle. For the month of November, the company planned for activity of 98 vehicles, but the actual level of activity was 58 vehicles. The actual materials and supplies for the month was $2,760.
Explanation / Answer
Cost of Material and Supplies Budgeted = 2030
Budgeted Vehicle Cost = 98*8 =784
Total = 2030+784 = $ 2814
The correct answer is $ 2814