Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

All techniques- Decision among mutually exclusive investments Pound Industries i

ID: 2658082 • Letter: A

Question

All techniques- Decision among mutually exclusive investments Pound Industries is attempting to select the best of three mutually exclusive projects. The initial investment and after-tax cash inflows associated with these projects are shown in the following table. Cash flows Initial investment (CF) Cash inflows (CF), t-1 to 5 Project C $120,000 $140,000 $150,000 $47,000 Project A $35,000 $46,500 a. Calculate the payback period for each project. b. Calculate the net present value (NPV) of each project, assuming that the firm has a cost of capital equal to 12%. c. Calculate the internal rate of return (IRR) for each project. d. Indicate which project you would recommend.

Explanation / Answer

Project A

Project B

Year

cash flow

present value of cash flow = cash flow/(1+r)^n r= 12%

Year

cash flow

present value of cash flow = cash flow/(1+r)^n r= 12%

0

-120000

-120000

0

-140000

-140000

1

35000

31250

1

46500

41517.86

2

35000

27901.79

2

46500

37069.52

3

35000

24912.31

3

46500

33097.78

4

35000

22243.13

4

46500

29551.59

5

35000

19859.94

5

46500

26385.35

NPV

sum of present value of cash flow

6167.167

NPV

sum of present value of cash flow

27622.09

IRR

Using IRR function in MS excel

14.05%

IRR

Using IRR function in MS excel

19.70%

Payback period

initial investment/annual cash flow

3.43

Payback period

initial investment/annual cash flow

3.01

Project C

Year

cash flow

present value of cash flow = cash flow/(1+r)^n r= 12%

0

-150000

-150000

1

47000

41964.29

2

47000

37468.11

3

47000

33453.67

4

47000

29869.35

5

47000

26669.06

NPV

sum of present value of cash flow

19424.48

IRR

Using IRR function in MS excel

17.11%

Payback period

initial investment/annual cash flow

3.19

Project

A

B

C

Final selection on the basis of capital budgeting technique

NPV

6167.167

27622.09

19424.48

Project B

Because NPV is highest

IRR

14.05%

19.70%

17.11%

Project B

Because IRR is highest

Payback period

3.43

3.01

3.19

Project B

Because PBP is lowest

Project A

Project B

Year

cash flow

present value of cash flow = cash flow/(1+r)^n r= 12%

Year

cash flow

present value of cash flow = cash flow/(1+r)^n r= 12%

0

-120000

-120000

0

-140000

-140000

1

35000

31250

1

46500

41517.86

2

35000

27901.79

2

46500

37069.52

3

35000

24912.31

3

46500

33097.78

4

35000

22243.13

4

46500

29551.59

5

35000

19859.94

5

46500

26385.35

NPV

sum of present value of cash flow

6167.167

NPV

sum of present value of cash flow

27622.09

IRR

Using IRR function in MS excel

14.05%

IRR

Using IRR function in MS excel

19.70%

Payback period

initial investment/annual cash flow

3.43

Payback period

initial investment/annual cash flow

3.01

Project C

Year

cash flow

present value of cash flow = cash flow/(1+r)^n r= 12%

0

-150000

-150000

1

47000

41964.29

2

47000

37468.11

3

47000

33453.67

4

47000

29869.35

5

47000

26669.06

NPV

sum of present value of cash flow

19424.48

IRR

Using IRR function in MS excel

17.11%

Payback period

initial investment/annual cash flow

3.19

Project

A

B

C

Final selection on the basis of capital budgeting technique

NPV

6167.167

27622.09

19424.48

Project B

Because NPV is highest

IRR

14.05%

19.70%

17.11%

Project B

Because IRR is highest

Payback period

3.43

3.01

3.19

Project B

Because PBP is lowest