Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Please solve the following question for Finance and step by step how to do it. A

ID: 2660131 • Letter: P

Question

Please solve the following question for Finance and step by step how to do it.


A proposed project will cost an estimated $2.2 billion to construct and will produce estimated OCF of $300 million a year for 15 years.  At the end of 15 years, the factory will be torn down at an estimated TCF of -$900 million. Calculate the projects expected NPV using a discount rate of 12%.


NPV is $614,500

NPV is -$321,167

NPV is -$485,555

NPV is -$1,056,741



NPV is $614,500

NPV is -$321,167

NPV is -$485,555

NPV is -$1,056,741

Explanation / Answer

Hi,


Please find the answer sa follows:


Initial Investemnt = 2.2 billion

Annual Cash Inflows = 300 million

Final Year Cash Flow = -900 million


NPV = -2.2 + .3/(1+.12)^1 + .3/(1+.12)^2 + .3/(1+.12)^3 + .3/(1+.12)^4 + .3/(1+.12)^5 + .3/(1+.12)^6 + .3/(1+.12)^7 + .3/(1+.12)^8 + .3/(1+.12)^9 + .3/(1+.12)^10 + .3/(1+.12)^11 + .3/(1+.12)^12 + .3/(1+.12)^13 + .3/(1+.12)^14 + .3/(1+.12)^15 -.9/(1+.12)^15 = -.321167 or -321167

Option B (NPV is -$321,167) is the correct answer.


Thanks.