Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Consider the following projects: CASH FLOWS ($) PROJECT C_0 C_1 C_2 C_3 C_4 C_5

ID: 2669362 • Letter: C

Question

Consider the following projects:
CASH FLOWS ($)
PROJECT C_0    C_1      C_2      C_3     C_4    C_5
A             -1000   +1000     0          0        0        0
B              -2000   +1000   +1000 +4000 +1000   +1000
C             -3000   +1000   +1000      0      +1000   +1000

If the opportunity cost of capital is %10, which projects have a positive NPV?


Calculate the payback period for each project.


Which project(s) would a firm using the payback rule accept if the cutoff period were three years?


Calculate the discounted payback period for each period.


Which project(s) would a firm using the discounted payback rule accept if the cutoff period were three years?

Explanation / Answer

For project A:

            Pay back period means the period at which all earnings are pay back itself is known as payback period.

Year

Cash flows($)

Cumulative cash flows($)

0

-1,000

-1,000

1

1000

0

2

0

3

0

4

0

5

0

            Here, the cash flow is payback at the end of the 1st year. Therefore payback period is 1 year.

For project B:

           

Year

Cash flows($)

Cumulative cash flows($)

0

-2,000

-2,000

1

1,000

-1,000

2

1,000

0

3

4,000

4

1,000

5

1,000

  The cash flows are payback itself at the end of the 2nd year. Therefore, Payback period is 2 years.

For project C:

Year

Cash flows($)

Cumulative cash flows($)

0

-3,000

-3,000

1

1,000

-2,000

2

1,000

-1,000

3

0

-1,000

4

1,000

0

5

1,000

           

Year

Cash flows($)

Present value factor at 10%

Discounted cash flows($)

Cumulative DCF

0

-1,000

1

-1,000

-1,000

1

1,000

0.9091

909.1

-91

2

0

0.8264

0

-91

3

0

0.7513

0

-91

4

0

0.6830

0

-91

5

0

0.6290

0

-91

  For this project there is no payback period. Because there are no cash flows to payback.

For Project B:      

Year

Cash flows($)

Present value factor at 10%

Discounted cash flows($)

Cumulative DCF

0

-2,000

1

-1,000

-1,000

1

1,000

0.9091

909.1

-91

2

1,000

0.8264

826.4

736

3

4,000

0.7513

3005.2

3,741

4

1,000

0.6830

683

4,424

5

1,000

0.6290

629

5,053

Year before recovery is = 2.

Remaining Years = (826.4 – 736)/826.4

                            = 0.11

            Payback period is 2.11 years.

For project C:

Year

Cash flows($)

Present value factor at 10%

Discounted cash flows($)

Cumulative DCF

0

-3,000

1

-1,000

-3,000

1

1,000

0.9091

909.1

-2,091

2

1,000

0.8264

826.4

-1,265

3

0

0.7513

0

-1,265

4

1,000

0.6830

683

-582

5

1,000

0.6290

629

48

Year before recovery is = 4.

Remaining years calculation = (629 – 48)/629

Year

Cash flows($)

Cumulative cash flows($)

0

-1,000

-1,000

1

1000

0

2

0

3

0

4

0

5

0