Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

AST Company is attempting to select among the two mutuallyexclusive projects bot

ID: 2705509 • Letter: A

Question

AST Company is attempting to select among the two mutuallyexclusive projects both of

which cost Rs. 100,000. The firm has a cost of capital equalto 13%. After-tax cash

inflows associated with each project are shown in thefollowing table :

Year Project A (Rs.) Project B (Rs.)

1 40,000 45,000

2 25,000 25,000

3 35,000 20,000

4 25,000 20,000

5 20,000 20,000

REQUIRED :

(i) Calculate the Payback Period for each project. (2+3)

(ii) Calculate the Net Present Value (NPV) of each project.(5+5)

(iii) Calculate the Internal Rate of Return (IRR) for eachproject. (6+6)

(IRR must be calculated by using

Explanation / Answer

Answer:

i) Calculate the Payback Period for eachproject.

Initial Investment = 100,000

Payback Period for Project A:

In year one, 40,000 will be covered, and (100,000-40,000) =60,000 should be covered.

In year two, further 25,000 will be covered, and (60,000-25,000)= 35,000 should be covered.

In year three, 35,000 will be covered, which we have to coverfrom the project.

So, our payback period is 3 years for ProjectA.

Payback Period for Project B:                 

In year one, 45,000 will be covered, and (100,000-45,000) =55,000 should be covered.

In year two, further 25,000 will be covered, and (55,000-25,000)= 30,000 should be covered.

In year three, 20,000 will be covered, and (30,000-20,000) =10,000 should be covered yet.

In year four, 20,000 will be covered, but we have to cover10,000 only,

So these 10,000 will take the time in years = 10,000/20,000 =0.5 years

OR 10,000 will take the time in months = 10,000/20,000 * 12 = 6months

OR 10,000 will take the time in days = 10,000/20,000 * 365 =182.5 days

So, payback period for Project B is 3.5 years, or 3years and 6 months or 3 years and 182.5 days.

ii) Calculate the Net Present Value (NPV) ofeach project.

NPV for Project A:

NPV = -Initial Investment + ? Cash Flows / (1+r)t

NPV = -100,000 + [40,000 / (1+0.13) 1] + [25,000 /(1+0.13) 2] + [35,000 / (1+0.13) 3] + [25,000/ (1+0.13) 4] + [20,000 / (1+0.13) 5]

NPV = -100,000 + [40,000 / (1.13) 1] + [25,000 /(1.13) 2] + [35,000 / (1.13) 3] + [25,000 /(1.13) 4] + [20,000 / (1.13) 5]

NPV = -100,000 + [40,000 / 1.13] + [25,000 / 1.2769] + [35,000 /1.442897] + [25,000 / 1.63047361] + [20,000 / 1.8424351793]

NPV = -100,000 + [35398.23] + [19578.67] + [24256.76] +[15332.97] + [10855.2]

NPV = 5421.83

NPV for Project B:

NPV = -Initial Investment + ? Cash Flows / (1+r)t

NPV = -100,000 + [45,000 / (1+0.13) 1] + [25,000 /(1+0.13) 2] + [20,000 / (1+0.13) 3] + [20,000/ (1+0.13) 4] + [20,000 / (1+0.13) 5]

NPV = -100,000 + [45,000 / (1.13) 1] + [25,000 /(1.13) 2] + [20,000 / (1.13) 3] + [20,000 /(1.13) 4] + [20,000 / (1.13) 5]

NPV = -100,000 + [45,000 / 1.13] + [25,000 / 1.2769] + [20,000 /1.442897] + [20,000 / 1.63047361] + [20,000 / 1.8424351793]

NPV = -100,000 + [39823] + [19578.67] + [13861] + [12266.37] +[10855.2]

NPV = -3615.76

iii) Calculate the Internal Rate of Return(IRR) for each project.

Internal rate of return (IRR) is a rate where, NPV becomes zerolet