Problem 11-6
NPV

Your division is considering two projects with the following cash flows (in millions):

What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55.
Project A    $   million
Project B    $   million

What are the projects' NPVs assuming the WACC is 10%? Round your answer to two decimal places. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55.
Project A    $   million
Project B    $   million

What are the projects' NPVs assuming the WACC is 15%? Round your answer to two decimal places. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55.
Project A    $   million
Project B    $   million

What are the projects' IRRs assuming the WACC is 5%? Round your answer to two decimal places.
Project A   %
Project B   %

What are the projects' IRRs assuming the WACC is 10%? Round your answer to two decimal places.
Project A   %
Project B   %

What are the projects' IRRs assuming the WACC is 15%? Round your answer to two decimal places.
Project A   %
Project B   %


0 1 2 3

Explanation / Answer

Hi,


Please find the answer as follows;


Part 1:


5%


NPV (Project A) = -11 + 4/(1+.05)^ + 7/(1+.05)^2 + 1/(1+.05)^3 = -7.56 million


NPV (Project B) = -20 + 12/(1+.05)^ + 5/(1+.05)^2 + 9/(1+.05)^3 = -3.70 million


10%


NPV (Project A) = -11 + 4/(1+.10)^ + 7/(1+.10)^2 + 1/(1+.10)^3 = -8.55 million


NPV (Project B) = -20 + 12/(1+.10)^ + 5/(1+.10)^2 + 9/(1+.10)^3 = -7.08 million


15%


NPV (Project A) = -11 + 4/(1+.15)^ + 7/(1+.15)^2 + 1/(1+.15)^3 = -9.21 million


NPV (Project B) = -20 + 12/(1+.15)^ + 5/(1+.15)^2 + 9/(1+.15)^3 = -9.57 million


Part 2:


5%


IRR (Project A) = 5.12%


IRR (Project B) = 15.43%


10%


IRR (Project A) = 5.12%


IRR (Project B) = 15.43%


15%



IRR (Project A) = 5.12%


IRR (Project B) = 15.43%


Notes:


IRR would continue to remain same irrespective of WACC.