Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Quattro, Inc. has the following mutually exclusive projects available. The compa

ID: 2708315 • Letter: Q

Question

Quattro, Inc. has the following mutually exclusive projects available. The company has historically used a 2.5-year cutoff for projects. The required return is 14 percent.


Year:                                                   Cash flow (A)                            Cash flow (B)

   0                                                           -$54,000                                     -$23,000

   1                                                              12,700                                         11,600

   2                                                               23,200                                        11,200

   3                                                               27,600                                        12,500

   4                                                               46,500                                         6,000



a.    What are the payback periods for project A and B? Based on payback rule, which project would the firm choose?

b.    What are the NPVs for project A and B? Based on NPV rule, which project, if any, should the company accept?

c.    What are the IRRs for project A and B? Based on IRR rule, which project, if any, should the company accept?

Based on the above answers, which project will you finally choose? Why?

Explanation / Answer

PAYBACK PERIOD FOR A = 2 + (54000-12700-23200)/27600

=2 + 0.25

=2.25 YEARS

PAYBACK PERIOD FOR B = 2 + (23000-11600-11200)/12500

=2+ 0.016

=2.016 YEARS

BASED ON PAYBACK PERIOD WE SHOUL CHOOSE B

NPV FOR A = 12700/(1.14) + 23200/(1.14)^2 + 27600/(1.14)^3 + 46500/(1.14)^4 - 54000

=21152.94

NPV FOR B = 11600/(1.14) + 11200/(1.14)^2 + 12500/(1.14)^3 + 6000/(1.14)^4 - 23000

=7783.1

BASED ON NPV WE SHOULD ACCEPT A

IRR

AT IRR , PV OF OUTFLOWS = PV OF INFLOWS

A

54000 = 12700/(1+IRR) + 23200/(1+IRR)^2 + 27600/(1+IRR)^3 + 46500/(1+IRR)^4

BY COMPUTING WE GET IRR = 28.5%

B

23000 = 11600/(1+IRR) + 11200/(1+IRR)^2 + 12500/(1+IRR)^3 + 6000/(1+IRR)^4

BY COMPUTING WE GET IRR = 30.94%

BASED ON IRR WE SHOUL CHOOSE B

4]ON THE WHOLE WE SHOULD TAKE NPV AS THE CTITERIA TO JUDGE WHICH PROJECT WE SHOULD ACCEPT. NPV IS THE SUPREME CRITERIAN TO JUDGE BETWEEN TWO MUTUALLY EXCLUSIVE PROJECTS . WE SHOULD ACCEPT PROJECT-A