Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

CSC is a mining firm based in Western Australia. One of its core activities is t

ID: 2727114 • Letter: C

Question

CSC is a mining firm based in Western Australia. One of its core activities is to develop mine fields. Currently, it is considering a project to develop a mine field in the Gibson Desert. The success of this project is largely dependent on the economy of China, where most of CSC’s ores are exported to. According to market research that CSC paid $200,000 for, the project will require an investment of $2,000,000 for extraction rights and the necessary equipment. It also shows that the project has 60% of succeeding, in which case CSC will get an annual net cash flow of $850,000 for ten years. If the project fails, CSC will get only $20,000 in the first two years and nothing after that because of the closure of the mine. CSC requires a 10 percent real return on projects of this type. What is the NPV of the project? All cash flows are expressed in real terms.

A) 1290597 B) 1147614 C) 1829061 D)1734002

Explanation / Answer

Success Case (p=60%)

Year

Cash Flow

PV Factor@ 10%

PV

0

                (2,000,000)

1.0000

            (2,000,000.00)

1

                      850,000

0.9091

                  772,727.27

2

                      850,000

0.8264

                  702,479.34

3

                      850,000

0.7513

                  638,617.58

4

                      850,000

0.6830

                  580,561.44

5

                      850,000

0.6209

                  527,783.12

6

                      850,000

0.5645

                  479,802.84

7

                      850,000

0.5132

                  436,184.40

8

                      850,000

0.4665

                  396,531.27

9

                      850,000

0.4241

                  360,482.98

10

                      850,000

0.3855

                  327,711.80

NPV

              3,222,882.04

Failure Case (p=40%)

Year

Cash Flow

PV Factor@ 10%

PV

0

                (2,000,000)

1.0000

            (2,000,000.00)

1

                        20,000

0.9091

                    18,181.82

2

                        20,000

0.8264

                    16,528.93

NPV

            (1,965,289.26)

Expected NPV of the Project =[0.6 x $ ]+[0.4 x - $ ]

                                                   =[0.6 x 3,222,882.04 ]+[0.4 x - $ 1,965,289.26]

                                                    = 1,933,729.22 + - $ 786,115.70

                                                   =$1,147,614

Option B correct

Success Case (p=60%)

Year

Cash Flow

PV Factor@ 10%

PV

0

                (2,000,000)

1.0000

            (2,000,000.00)

1

                      850,000

0.9091

                  772,727.27

2

                      850,000

0.8264

                  702,479.34

3

                      850,000

0.7513

                  638,617.58

4

                      850,000

0.6830

                  580,561.44

5

                      850,000

0.6209

                  527,783.12

6

                      850,000

0.5645

                  479,802.84

7

                      850,000

0.5132

                  436,184.40

8

                      850,000

0.4665

                  396,531.27

9

                      850,000

0.4241

                  360,482.98

10

                      850,000

0.3855

                  327,711.80

NPV

              3,222,882.04