Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Problem 13-16 WACC and NPV Och, Inc., is considering a project that will result

ID: 2729309 • Letter: P

Question

Problem 13-16 WACC and NPV Och, Inc., is considering a project that will result in initial aftertax cash savings of $1.70 million at the end of the first year, and these savings will grow at a rate of 3 percent per year indefinitely. The firm has a target debt–equity ratio of .85, a cost of equity of 11.0 percent, and an aftertax cost of debt of 3.8 percent. The cost-saving proposal is somewhat riskier than the usual projects the firm undertakes; management uses the subjective approach and applies an adjustment factor of +2 per cent to the cost of capital for such risky projects. What is the maximum initial cost of company would be willing to pay for the project? (Do not round intermediate calculations. Enter your answer in dollars, not millions of dollars, i.e. 1,234,567.) Maximum cost $

Explanation / Answer

WACC = cost of debt x weight of debt + cost opf equity x weight of equity + adjustment factor

= [0.038 x 0.85/1.85 + 0.11 x 1/1.85] + 2

= 7.69% + 2 = 9.69%

Maximum intial cost that the company should be willing to pay for the project =

= (Initial after tax cash savings + growth rate) / (WACC - growth rate)

= [1700000 x (1 + 0.03)] / (0.0969 - 0.03)

= 1751000 / 0.0669

= $26,173,393

Therefore, the maximum initial cost of company would be willing to pay for the project = $26,173,393