14. Identify the document that is developed from the project scope statement, the project work breakdown structure (WBS) and the WBS dictionary that will be part of the procurement documents package. A. Contract Management Plan. B. Make-or-Buy Analysis. C. Organizational Process Assets. D. Statement of Work. 14. Identify the document that is developed from the project scope statement, the project work breakdown structure (WBS) and the WBS dictionary that will be part of the procurement documents package. A. Contract Management Plan. B. Make-or-Buy Analysis. C. Organizational Process Assets. D. Statement of Work.Explanation / Answer
Answer: D. Statement of Work.