Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Portland Products is considering the purchase of one of three mutually exclusive

ID: 2767227 • Letter: P

Question

Portland Products is considering the purchase of one of three mutually exclusive projects for increasing production efficiency. The firm plans to use a 14% cost of capital to evaluate these equal-risk projects. The initial investment and annual cash inflows over the life of each project are shown in the following table. a. Calculate the NPV for each project over its life. Rank the projects in descending order on the basis of NPV. b. Use the annualized net present value (ANPV) approach to evaluate and rank the projects in descending order on the basis of ANPV. c. Compare and contrast your findings in parts a and b. Which project would you recommend that the firm purchase? Why?

Explanation / Answer

Project X

Year

Cash flow

PV Factor @ 14%

PV

0

-78,000

1

   (78,000.00)

1

17,000

0.8772

      14,912.28

2

25,000

0.7695

      19,236.69

3

33,000

0.6750

      22,274.06

4

41,000

0.5921

      24,275.29

NPV

        2,698.32

Project Y

Year

Cash flow

PV Factor @ 14%

PV

0

-52,000

1

   (52,000.00)

1

28,000

0.8772

      24,561.40

2

38,000

0.7695

      29,239.77

NPV

        1,801.17

Project Z

Year

Cash flow

PV Factor @ 14%

PV

0

-66,000

1

   (66,000.00)

1

15,000

0.8772

      13,157.89

2

15,000

0.7695

      11,542.01

3

15,000

0.6750

      10,124.57

4

15,000

0.5921

        8,881.20

5

15,000

0.5194

        7,790.53

6

15,000

0.4556

        6,833.80

7

15,000

0.3996

        5,994.56

8

41,000

0.3506

      14,372.92

NPV

      12,697.49

a.

Project X

Project Y

Project Z

NPV

    2,698.32

    1,801.17

    12,697.49

Rank

II

III

I

b.

Project X

Project Y

Project Z

Sum Of PV

1.6467

4.6389

4.6389

Annualized NPV

    1,638.66

       388.28

      2,737.20

Rank

II

III

I

c. The firm should purchase Project Z as it gives highest NPV and ANPV value.

Project X

Year

Cash flow

PV Factor @ 14%

PV

0

-78,000

1

   (78,000.00)

1

17,000

0.8772

      14,912.28

2

25,000

0.7695

      19,236.69

3

33,000

0.6750

      22,274.06

4

41,000

0.5921

      24,275.29

NPV

        2,698.32