Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Higher Ground Company is presented with the following two mutually exclusive pro

ID: 2773018 • Letter: H

Question

Higher Ground Company is presented with the following two mutually exclusive projects. The required return for both projects is 15 percent.

What is the IRR for each project? (Do not include the percent signs (%). Enter rounded answers as directed, but do not use the rounded numbers in intermediate calculations. Round your answers to 2 decimal places (e.g., 32.16).)

What is the NPV for each project? (Do not include the dollar signs ($). Enter rounded answers as directed, but do not use the rounded numbers in intermediate calculations. Round your answers to 2 decimal places (e.g., 32.16).)

Higher Ground Company is presented with the following two mutually exclusive projects. The required return for both projects is 15 percent.

Explanation / Answer

Answer (a)

Project M = IRR 35%

Project N = IRR 24%

Answer (b)

NPV of Project M = $ 59,530.30

NPV of Project N = $ 63,095.40

Answer (c)

As NPV is positive both the projects are acceptable.

Working

Year

Project M

Project N

0

-$141,000

-$364,000

1

64,400

148,000

2

82,400

189,000

3

73,400

133,000

4

59,400

119,000

Required Return = 15% or 0.15

If r is the required rate of return and CF1,CF2,CF3,CF4 are cash flows in years 1,2,3,4, then NPV can be calculated using the formula

NPV = - Initial Investment + CF1 / 1+r + CF2 / (1+r)^2 + CF3 / (1+r)^3 + CF4/(1+r)^4

The rate of return r will be known as Internal Rate of Return (IRR) of the project if NPV= 0. That is

- Initial Investment + CF1 / 1+r + CF2 / (1+r)^2 + CF3 / (1+r)^3 + CF4/(1+r)^4 = 0

Calculation of IRR for Project M

-$ 141,000 + 64,400 / 1+r + 82,400 / (1+r)^2 + 73,400 / (1+r)^3 + 59,400/(1+r)^4 = 0

Using IRR function in Excel the value of r for Project M is 35%

Calculation of IRR for Project N

-$364,000+ 148,000 / 1+r + 189,000 / (1+r)^2 + 133,000 / (1+r)^3 + 119,000/(1+r)^4 = 0

Using IRR function in Excel the value of r for Project N is 24%

Required Return = 15% or 0.15

NPV = - Initial Investment + CF1 / 1+r + CF2 / (1+r)^2 + CF3 / (1+r)^3 + CF4/(1+r)^4

Calculation of Discounting Factor

1/(1.15) = 0.8696

1/1.15^2 = 1/1.3225 = 0.7561

1/1.15^3 = 1/1.520875 = 0.6575

1/1.15^4 = 1/1.74900625 = 0.5718

Year

Discounting factor

Project M

Discounted Flow

Project N

Discounted Flow

1

0.8696

64,400

56,002.24

148,000

128,700.80

2

0.7561

82,400

62,302.64

189,000

142,902.90

3

0.6575

73,400

48,260.50

133,000

87,447.50

4

0.5718

59,400

33,964.92

119,000

68,044.20

Total Discounted Cash Flow

200,530.30

427,095.40

NPV of Project M = -$ 141,000 + $ 200,530.30 = $ 59,530.30

NPV of Project N = - $ 364,000 + $ 427,095.40 = $ 63,095.40

Year

Project M

Project N

0

-$141,000

-$364,000

1

64,400

148,000

2

82,400

189,000

3

73,400

133,000

4

59,400

119,000