Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Instructions: Please answer questions A-D below. I can\'t award credit if A-D is

ID: 2782406 • Letter: I

Question

Instructions: Please answer questions A-D below. I can't award credit if A-D isn't answered completely.

Primus Corp. is planning to convert an existing warehouse into a new plant that will increase its production capacity by 45 percent. The cost of this project will be $7,125,000. It will result in additional cash flows of $1,875,000 for the next eight years. The company uses a discount rate of 12 percent.

A. What is the payback period?

B. What is the NPV for this project ?

C. What is the IRR?

D. Based on the results give a suggestion to Primas Corp?

Explanation / Answer

Payback Period

Payback is the time it takes for the project to return the initial capital incurred on project.

Since the cash inflow is same through out the year

Payback period = Initial cash out flow/Annual cash inflow

                              = 7125000/1875000

                              = 3.8 years

NPV

NPV is the difference between present value of all cash inflow and initial cost of asset or project. All the future cash flows are discounted using discounting rate or required rate and the sum of all the discounted cash flows will be subtracted with initial cost.       

NPV = Sum of future cash inflow - initial cost

Pls refer below table for NPV calculation,

Year

Cash Inflow

PV factor

PV of cash flow

1

1875000

0.892857

1674107.143

2

1875000

0.797194

1494738.52

3

1875000

0.711780

1334587.965

4

1875000

0.635518

1191596.397

5

1875000

0.567427

1063925.354

6

1875000

0.506631

949933.3522

7

1875000

0.452349

848154.7788

8

1875000

0.403883

757281.0525

Total

9314324.563

Initial cost

7125000

NPV

2189324.563

Decision rule for NPV is that project is accepted if NPV is positive and rejected if it is in negative                                                                                                          

IRR

Internal rate of return is the rate at which if we discount all the future cash flows, the resulting NPV will be zero, it is minimum rate of return that management seeks from the project, IRR of te asset/project must be greater than the required rate of return, otherwise it will not be feasible for the management to accept the project. Best way to calculate IRR is using Excel.                           

Year

Cash flow

0

-7125000

1

1875000

2

1875000

3

1875000

4

1875000

5

1875000

6

1875000

7

1875000

8

1875000

IRR

20.33%

Formula

=IRR(J21:J31)

Project is accepted when IRR is more than the required rate of return ( 12%)

Since all the three capital budgeting techniques shows a positive result, so project should be accepted.

                                               

Year

Cash Inflow

PV factor

PV of cash flow

1

1875000

0.892857

1674107.143

2

1875000

0.797194

1494738.52

3

1875000

0.711780

1334587.965

4

1875000

0.635518

1191596.397

5

1875000

0.567427

1063925.354

6

1875000

0.506631

949933.3522

7

1875000

0.452349

848154.7788

8

1875000

0.403883

757281.0525

Total

9314324.563

Initial cost

7125000

NPV

2189324.563