CLICK AND DRAG QUESTION:EXAMINE the various projects is visible when hoveing ove
ID: 2784911 • Letter: C
Question
CLICK AND DRAG QUESTION:EXAMINE the various projects is visible when hoveing ove the daggable project name) and place them ascending order based on their net present value (NPV). While no calculationd sare absolutely required, as the projects may be ordered bsed on their investment, cash inflows, and required rate of return, the NPVs ay certainly be computed bsed on the information given. To assistin determining into which area each project name needs to be dropped, the rop areas are labeled with the respective NPVs. PROJECT A PROJECT B PROJECT C PROJECTD PROJECT E PROJECT F PROJECT G PROJECT H: NPV equals -$37,741; NPV equals $162,259; NPV equals $304,615; NPV equals $399,173; NPV equals $62,259; NPV equals $233,437; NPV equals $384,334; NPV equals $414,500
Explanation / Answer
As the NPV given in the question are
Project A: -37,741
Project B: 162,259
Project C: 304,615
Project D: 399,173
Project E: 462,259
Project F: 233,437
Project G: 384,334
Project H: 414,500
Thus arranging the Projects according to their NPVs in an ascending order as below:
Project A: -37,741
Project B: 162,259
Project F: 233,437
Project C: 304,615
Project G: 384,334
Project D: 399,173
Project H: 414,500
Project E: 462,259
To say the ascending order based on their ner present value is Project A, Project B, Project F, Project C, Project G, Project D, Project H, Project E.