Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Blooper’s analysts have come up with the following revised estimates for its mag

ID: 2788549 • Letter: B

Question

Blooper’s analysts have come up with the following revised estimates for its magnoosium mine: Range Pessimistic Optimistic Initial investment + 25 % – 15 % Revenues – 20 % + 25 % Variable costs + 15 % – 20 % Fixed cost + 40 % – 45 % Working capital + 50 % – 20 % A. Inputs

Initial investment ($ thousands) 10,000

Salvage value ($ thousands) 2,000

Initial revenues ($ thousands) 15,000

Variable costs (% of revenues) 40.0%

Initial fixed costs ($ thousands) 4,000

Initial total expenses ($ thousands) 10,000

Inflation rate (%) 5.0%

Discount rate (%) 12.0%

Receivables (% of sales) 16.7%

Inventory (% of next year's costs) 15.0%

Tax rate (%) 35.0%

Year: 0 1 2 3 4 5 6

B. Fixed assets

Investments in fixed assets 10,000

Sales of fixed assets 1,300

Cash flow from fixed assets -10,000 1,300

C. Operating cash flow

Revenues 15,000 15,750 16,538 17,364 18,233

Variable expenses 6,000 6,300 6,615 6,946 7,293

Fixed expenses 4,000 4,200 4,410 4,631 4,862

Depreciation 2,000 2,000 2,000 2,000 2,000

Pretax profit 3,000 3,250 3,513 3,788 4,078

Tax 1,050 1,138 1,229 1,326 1,427

Profit after tax 1,950 2,113 2,283 2,462 2,650

Operating cash flow 3,950 4,113 4,283 4,462 4,650

D. Working capital

Working capital 1500 4075 4,279 4,493 4,717 3,039 0

Change in working capital 1,500 2,575 204 214 225 -1,679 -3,039

Cash flow from investment in working capital -1,500 -2,575 -204 -214 -225 1,679 3,039 0.408 0.408 0.408 0.408 0.250

E. Project valuation

Total project cash flow -11,500 1,375 3,909 4,069 4,238 6,329 4,339

Conduct a sensitivity analysis for each variable and range and compute the NPV for each. Use Spreadsheet 10.1 and accompanying data as a starting point for the analysis. (Do not round intermediate calculations. Negative amounts should be indicated by a minus sign. Enter your answers in thousands rounded to the nearest whole dollar.))

project NPV

PESSIMISTIC EXPECTED OPTIMISTIC

INITIAL INVESTMENT

REVENUES

VARIABLE COST

FIXED COST

WORKING CAPITAL

Explanation / Answer

Sensitivity Analysis :Sensitivity analysis is an analysis that finds out how sensitive an output is to any change in an input while keeping other inputs constant.

Firms use the expected cash flows from each project to calculate its NPV and green light projects with NPV > 0.

Sensitivity analysis asks how the NPV of a project changes when actual cash flows are higher or lower than expected cash flows. One way to incorporate uncertainty into the capital budgeting process is to compare the NPV of a project under two (or more scenarios)

•Good versus Bad

•Pessimistic versus Optimistic

When the project’s NPV is positive under all scenarios, the firm should definitely undertake the project; when the project’s NPV is negative under some scenarios, the firm needs to weigh the positive outcomes against the negative outcomes. When making these decisions, leverage matters.

NPV of Each part:-

In that case NPV is positive.

table will sent very soon with data

Range Pessimistic Optimistic Intial investment -25% -15% Revenue -20% +25% Variable cost +15% -20% Fixed Cost +40% -45% Working capital +50% -20%