Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

The following Information appliles to the questions displayed below Trico Compan

ID: 2796764 • Letter: T

Question

The following Information appliles to the questions displayed below Trico Company set the following standard unit costs for its single product. Direct materials (26 lbs.@ $4 per lb.) Direct labor (8 hrs. $8 per hr.) Factory overhead-variable (8 hrs.@$5 per hr.) Factory overhead-fixed (8 hrs. @ $7 per hr.) $104.00 64.00 40.00 56.00 Total standard cost $264.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 40,000 units per quarter. The following flexible budget information is available Operating Levels 70% 28,000 224,000 80% 32,000 256,000 90% Production in units Standard direct labor hours Budgeted overhead 36,000 288,000 Fixed factory overhead Variable factory $ 1.792.000 $. 1.792.000 $. 1.792.000 $1.120,000 1,280,000 1.440,000 During the current quarter, the company operated at 90% of capacity and produced 36,000 units of product actual direct labor totaled 280,000 hours. Units produced were assigned the following standard costs: Direct materials (936,000 lbs.@$4 per lb.) Direct labor (288,000 hrs.@$8 per hr) Factory overhead (288,000 hrs. $12 per hr.) $ 3,744,000 2,304,000 3,456,000 Total stanclard cost $9,504,000 Actual costs incurred during the current quarter follow: $3.817100 Direct materials (931,000 lbs. $4.10 per lb.) Direct labor (280,000 hrs.@$775 per hr.) Fixed factory overhead costs 2.170,000 2.483.019 2,324,528 Variable factory overhead costs Total actual costs $10,794,647

Explanation / Answer

Part - A

Material Variance

Where,

SQ = Standard Quantity, SP = Standard Price, AQ=Actual Quantity , AP = Actual Price

Material Cost Variance = 1-2

= 3744000-3817100

= 73,100 Adverse

Material Price Variance = 3-2

=3724000-3817100

=93,100 Adverse

Material Quantity Variance =1-3

=3744000-3724000

=20,000 Favouable

Part - B

Direct Labour Variance

Where,

SH = Standard Hours, SR = Standard Rate, AH = Actual hour, AR = Actual Rate

Direct Labour Variance = 1-2

=2304000-2170000

=134,000 Favourable

Labour Rate Variance = 3-2

=2240000-2170000

=70,000 Favouable

Labour Efficiency Variance = 1-3

=2304000-2240000

=64,000 Favouable

Part - C

Variable Overhead Variance

Variable Overhead Volume Variance = Budgeted Overhead - Actual Overhead

= 1,440,000-2,324,528

=884,528 Adverse

Part - D

Fixed Overhead Volume Variance

Volume Variance = Budgeted Fixed overhead - Actual Fixed Overhead

=1,792,000-2483019

=691,019 Adverse

(1) (2) (3) Standard Actual SQ*SP AQ*AP AO*SP 936000*4 931000*4.10 931000*4 3,744,000 3,817,100 3,724,000