Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Consider the following two mutually exclusive projects: Year Cash Flow (A) Cash

ID: 2796806 • Letter: C

Question

Consider the following two mutually exclusive projects:

Year

Cash Flow (A)

Cash Flow (B)

0

- $455,000

-$65,000

1

58,000

31,000

2

85,000

28,000

3

85,000

25,500

4

572,000

19,000

Your required rate of return is 15 percent.

a) If you apply the payback period criterion, which investment will you choose? Why?

b) If you apply the discounted payback period criterion, which investment will you choose? Why?

c)If you apply the NPV criterion, which investment will you choose? Why?

d) If you apply the IRR criterion, which investment will you choose? Why?

e) If you apply the profitability index criterion, which investment will you choose? Why?

f) Based on your answers in (a) through (e) above, which project will you finally choose? Why?

Year

Cash Flow (A)

Cash Flow (B)

0

- $455,000

-$65,000

1

58,000

31,000

2

85,000

28,000

3

85,000

25,500

4

572,000

19,000

Explanation / Answer

a.

Payback period = A + B/C

Where,
A = Last period with a negative cumulative cash flow;
B = Absolute value of cash flow at the end of the period A;
C = cash flow during the period after A.

Project A:

Payback period = 3 + 227000/572000 = 3.40 years

Project B:

Payback period = 2 + 6000/25500 = 2.24 years

Choose project B since payback period is least.

b.

Project A:

DPB = 3 + 284404.13/327042.86 = 3.87 years

Project B:

DPB = 3 + 104.79/10863.31 = 3.01 years

Choose project B, since DPB is least

c.

NPV is calculated by discounting the cashflows

PV = C/(1+r)^n

C - Cashflow

r - Discount rate

n - years to the cashflow

Project A:

Project B:

Choose project A, since NPV is higher

d.

IRR is the rate at which NPV = 0

Project A:

NPV = -455000 + 58000/(1+r)^1 + 85000/(1+r)^2 + 85000/(1+r)^3 + 572000/(1+r)^4 = 0

By trail and error, r = 18.15%

Project B:

NPV = -65000 + 31000/(1+r)^1 + 28000/(1+r)^2 + 25500/(1+r)^3 + 19000/(1+r)^4 = 0

r = 23.65%

Choose project B, since IRR is higher.

e.

PI = (NPV+Initial investment)/Initial investment

Project A:

PI = (42638.73+455000)/455000 = 1.09

Project B:

PI = (10758+65000)/65000 = 1.17

Choose project B, since PI is higher.

f. Choose project A, since the NPV is higher than project B.

NPV is the first criteria to be used in evaluating the projects.

Year Cashflow (A) Cumulative 0 -455000.00 -455000.00 1 58000.00 -397000.00 2 85000.00 -312000.00 3 85000.00 -227000.00 4 572000.00 345000.00