The following information pertains to questions 32 to 35.

Energy Corp. has a market capitalization of $15 billion and debt with market value of $5 billion. Energy will keep its current Debt-to-Equity ratio constant. The equity cost of capital is rE = 10% and the cost of debt is rD = 6%. The corporate tax rate is 35%. Assume a market risk premium of 6% and a risky-free rate of 5%.

The firm is considering an expansion project (i.e., same risk as the firm’s assets) with the following cash flows:

Year 0 1 2

Free Cash Flows ($M) -100 70 120

32. What is the Net Present Value of the project? (A) $ 65.00M (B) $ 66.51M X Correct (C) $ 70.00M (D) $ 72.24M

33. Assume (correctly or incorrectly) that the Net Present Value of the project is $65M. How much new equity will Energy need to start the project? (A) $ 75.00M (B) $ 58.75M X Correct (C) $ 50.50M (D) $ 45.00M

34. Energy’s debt Beta is closest to: (A) 0.15 (B) 0.17 X Correct (C) 0.20 (D) 0.23

35. Assume that the project is not an expansion project within Energy’s line of business (i.e., different risk). BigKup, a public firm, is believed to meet the requirements for a comparable firm. BigKup has an equity Beta of 1.5 and a debt-to-equity ratio of 1. BigKup can borrow at the risk free rate. What should the project’s discount rate be if the project were financed with equity only? (A) 9.5% X Correct (B) 10.5% (C) 11.0% (D) 14.0%

Explanation / Answer

first find wacc
wacc=(wt of debt*after tax cost of debt)+(wt of equity*cost of equity)
wt of debt=5/(5+15)=25%
wt of equity=75%
after tax cost of debt=6%*(1-35%)=3.9%
cost of equity=10%
WACC=(25%*3.9%)+(75%*10%)=8.475%
NPV= present value of future cash flows
32) NPV=-100+(70/(1+8.475%)^1)+(120/(1+8.475%)^2)
=66.51mn