Consider the following project; for which activities is it possible that the sla

ID: 2923119 • Letter: C

Question

Consider the following project; for which activities is it possible that the slack can be greater than zero?

Activity

Immediate Predecessors

A

None

B

A

C

A

D

C

E

B,D

F

E

Only activities B or C could have slack, but they could not both have slack.

Only activities B or D could have slack, but they could not both have slack.

Only activities A or F could have slack, but they could not both have slack.

It is possible for either both of activities C and D to have slack, OR for activity B to have slack.

It is possible for any or all activities in this project to have slack.

Activity

Immediate Predecessors

A

None

B

A

C

A

D

C

E

B,D

F

E

Explanation / Answer

Only activities B or C could have slack, but they could not both have slack.

Option A is correct.