Assume that activity M has the following times: Early start time (ES) = 14 days
ID: 2923129 • Letter: A
Question
Assume that activity M has the following times:
Early start time (ES) = 14 days
Early finish time (EF) = 22 days
Latest start time (LS) = 16 days
Latest finish time (LF) = 24 days
Which of the following statements is TRUE about activity M?
Activity M takes 2 days to complete
Activity M has 2 days of slack time
Activity M is on the critical path
Activity M is the first activity of the project
None of the above are true
a.Activity M takes 2 days to complete
b.Activity M has 2 days of slack time
c.Activity M is on the critical path
d.Activity M is the first activity of the project
e.None of the above are true
Explanation / Answer
Slack time of the project
= Latest start - earliest start
= 16 - 14 = 2
Only correct answer is given in b.