Use the following information to answer questions 29 and30: Trendprojection is u
ID: 2950777 • Letter: U
Question
Use the following information to answer questions 29 and30:
Trendprojection is used to predict quarterly demand for a product. Datastarting with quarter 1 of year 2007 was used to generate thefollowing trend equation: Y = 250 - 2.5t. Seasonal (quarterly)indices are also computed: Quarter 1 = 1.5; Quarter 2 = 0.8;Quarter 3 = 1.1; and Quarter 4 = 0.6.
21) What is the seasonally-adjusted forecast for quarter 2 of2009 (rounded to the nearest integer)?
a. 188
b. 180
c. 256
d. 245
22) What is the seasonally-adjusted forecast for quarter 4 of2009?
a. 140
b. 189
c. 138
d. 132