Assume that 20 parts are checked each hour and that X denotesthe number of parts in the sample of 20 that require rework. Partsare assumed to be independent with respect to rework. c) If the rework percentage increases to 4%, what is theexpected number of hours until X exeeds 1? Assume that 20 parts are checked each hour and that X denotesthe number of parts in the sample of 20 that require rework. Partsare assumed to be independent with respect to rework. c) If the rework percentage increases to 4%, what is theexpected number of hours until X exeeds 1?Explanation / Answer
Let X has a negative binomial distribution with p = 0.04 and r =1
So, the expected number of hours is given by, E(X)=1/0.04=25.