QUESTION 17 Use the Residential Construction Plan file provided as part of your
ID: 3148862 • Letter: Q
Question
QUESTION 17 Use the Residential Construction Plan file provided as part of your semestor project 1. The project start date is 10/1/17 2 The status date is 12/10/17 3. In addition to the "Federal Holidays' schedule used in your Snal projed betocen 101117 and 90018, geane enter thetolowing hoidays Fat treak on theid Mand and Tuesday in Oct 2017, extended Thanksgiving to include Nov 22-24, 2017, and extonded Chistmas holday for Dec 25 29,2017 4. $/hr rate is $100 for all resources 5 Use the following information for activities that start by 12/1/17 in original schedule after updating the start date as 10/1/17 The first activity (Finalize plans and develop estimate with owner, architect) starts on 1017 Each activity takes two extra day to finish so the actual durations will be plamd dmin. . You must maintain the predecessor relationship i o M predecessor activity ls frelished lat Based on the above information, find the valuos for SV, CV. and EAC You most upload your toal MSpedh Attach File Browse My 2 points SaveA QUESTION 18 An agreement included the target price of S 180 000 while the incen ve fes were set a 0% of cost difere ce bet project ended up being $120,000, the total amount to be paid to the contractor should be S n actual o trdt ge rice" te S0%ofcostanerencebetween actual-target price "wah.costat Click Save and Submit to save and submit Click Save All Answers to sarealiensersExplanation / Answer
Target price = 180,000$
Incentive is 20% of the cost difference between actual and target price
Actual cost = 120,000$
So the difference between actual and target price that came as savings = 180000-120000 = 60,000
20% of 60,000 = 12,000$
Thus, the amount to be paid to the contractor should be = 12,000 $