roiect Planning 181 ducting theusing the critical path method, you determine the
ID: 328506 • Letter: R
Question
roiect Planning 181 ducting theusing the critical path method, you determine the late st a. forward pass b. backward pass c. slack analysis d. critical path evaluation 7. The critical path is defined as a. the most important activities b. the path of longest duration the activities with the least amount of slack c. d. band c All of the above e. 8. How does the theory of constraints explain the critical path method? a. By emphasizing that the goal to make money should be a primary objective b. By relating the critical path to a bottleneck that determines the rate of throughput By distinguishing between free and total slack in terms of throughput d. c. By allowing SON, FNLT, and SNET constraints to be used in activity definitions 9. A Gantt chart is useful for communicating project status b. a. controlling project costs c. evaluating free and total slack measuring project quality 10. PMSSs are useful for a. helping the project team develop the WBS b. ensuring the quality of project deliverables c. determining what information the stakeholders should receive d. updating the project with changes to statusExplanation / Answer
6. B. Backward Pass
7. A. The most important activities
8. B. By relating the critical path to the bottleneck that determines the rate of throughput
9. A. Communicating project status
10. B ensuring the quality of project deliverables