Based on the following PERT chart: A(6) Start End F(5) How many tasks are there
ID: 331689 • Letter: B
Question
Based on the following PERT chart: A(6) Start End F(5) How many tasks are there for the project? What is the total task time for the project? G(4) H(5) What is the critical time for the project? Based solely on the critical time and average time, what is the lowest finishing time for the project if the project is being completed by two processors? Based solely on the critical time and average time, what is the lowest finishing time for the project if the project is being completed by three processors?Explanation / Answer
Total number of task = 8
Total task time for the project = 6+11+ 8 = 26
average time for the project = 24+26/2 = 25