Can someone provide me with the correct answers, I am stuck. Process \"capabilli
ID: 334374 • Letter: C
Question
Can someone provide me with the correct answers, I am stuck.
Process "capabillity" means the ablty to produce at high True O False True False Process "capability" means the ablity alue: 4.00 polnts The Cp measure of capabllty assumes.. value: 4.00 polnts The Cp measui O A high O The pt O The pt The Cpk measure uses which of. The Cpk measure uses which of the following as Inputs? ?Upper specification limit Lower specification lImlt The pr OAfour ? O ProduThree sigma The average velue: 1.00 polnts The Cpk measure uses which of... The Cpc measure uses wh?h of the following as inputs? Upper specicetion linit ? Lower specification limit Three sigma The evelage Check All ThatApplyExplanation / Answer
FALSE
it means the ability of a process to produce within the specified limits.
-------------------------------------------------------------------------------------------------
5 the production distribution is centered
--------------------------------------------------------------
6.
formula to calculate the cpk
cpk=min(USL- x / 3sigma ; x-LSL / 3 sigma)
so the answer is all the options
USL
LSL
3 sigma
the average