Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

A chip manufacturer wants to estimate the average fill for a package of chips. T

ID: 3358752 • Letter: A

Question

A chip manufacturer wants to estimate the average fill for a package of chips. The data in the table represents a 1 in 100 systematic sample for 1 day’s production. Estimate the mean fill in ounces. Place a bound on the error of estimation. Assume the company produces about 3600 bags of chips per day.



Sum of values listed = 568.580; Sum of values^2 = 8980.283817
s^2 = .07454

15.79
15.78
15.87
15.65
15.68
15.73 15.74
15.9
15.89
15.72
15.78
15.82 15.83
15.86
15.72
15.78
15.85
15.76 15.72
15.9
15.6
15.7
15.83
15.86 15.88
15.83
15.76
15.82
15.9
15.86 15.85
15.75
15.85
15.75
15.79
15.78

Explanation / Answer

Mean Estimate =Sum of values listed / No. of values

= 568.580 /36

= 15.794

Error estimate = S^2 /n

= 0.07454 /36

=0.0455