Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Two efficiency indicators that reflect the cost and schedule performance of a pr

ID: 337350 • Letter: T

Question

Two efficiency indicators that reflect the cost and schedule performance of a project are:

a. Cost projection index (CPI) and schedule projection index (SPI)

Actual cost (AC) and Planned value (PV)

c. Cost performance index (CPI) and Schedule performance index (SPI)

d. Cost pricing index (CPI) and schedule performance index (SPI)

a. Cost projection index (CPI) and schedule projection index (SPI)

b.

Actual cost (AC) and Planned value (PV)

c. Cost performance index (CPI) and Schedule performance index (SPI)

d. Cost pricing index (CPI) and schedule performance index (SPI)

Explanation / Answer

Two efficiency indicators that reflect the cost and schedule performance of a project are:

a. Cost projection index (CPI) and schedule projection index (SPI)

Actual cost (AC) and Planned value (PV)

c. Cost performance index (CPI) and Schedule performance index (SPI)

d. Cost pricing index (CPI) and schedule performance index (SPI)

a. Cost projection index (CPI) and schedule projection index (SPI)

b.

Actual cost (AC) and Planned value (PV)

c. Cost performance index (CPI) and Schedule performance index (SPI)

d. Cost pricing index (CPI) and schedule performance index (SPI)