Problem 5-5 Your project to obtain charitable donations is now 50 days into a planned 60-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 44 days of the project and to bring in $26,300. Even though we are 50 days into the project, we still see that we have only 88% of this activity complete. The second activity relates to company donations and is scheduled to run for 50 days starting on day 6 and extending through day 56. We estimate that even though we should have (44/50,88% of this activity complete it is actually only 55% complete. This part of the project was scheduled to bring in $151,300 in donations. The final activity s for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $52,600. So far $175,600 has actually been brought in on the project. 0 Calculate the schedule variance, schedule performance index, cost variance and cost (actually value in this case) performance index. (Negative values should be indicated by a minus sign. Do not round intermediate calculations. Round your dollar amounts to the nearest whole number. Round your "performance index" values to 3 decimal places.) Schedule variance Schedule performance index Cost variance Cost performance indexExplanation / Answer
At 50 days
Task 1
Planned Completion = 100%
Actual Completion = 88%
Planned Value = 26300
Earned value = 88%*26300 = 23144
Task2
Planned Completion = 44/50 = 88%
Actual completion = 55%
Budget amount = 151300
Planned Value = 88%*151300 = 133144
Earned value = 55%*151300 = 83215
Task 3
Start date = 50 Complete date = 60
Planned Completion = 1/10 = 10%
Actual completion = 0%
Budget = 52600
Planned value = 10%*52600 = 5260
Earned value = 0%*52600 = 0
Overall Project level
Planned value,PV = sum of all three task planned value = 26300 +133144 +5260 = 164704
Earned value,EV = sum of all three task earned value =23144 + 83215 + 0 = 106359
Actual Cost ,AC = 175600
Schedule variance = EV-PV =106359 - 164704 = $ - 58345
Schedule Performance Index, SPI = EV/PV = 106359/164704 = 0.646
Cost Variance = EV-AC = 106359-175600 = $ -69241
Cost Performance Index = EV/AC = 106359/ 175600 = 0.606