It took a contractor 7000 hours to manufacture their first unit of an item. If the contractor expects to achieve a 94% unit learning curve, how many hours would be required to manufacture units 76-100? (Use the tables provided in the lesson). A) 507,683 B) 117,382 C) 507,717 D) 112,627 It took a contractor 7000 hours to manufacture their first unit of an item. If the contractor expects to achieve a 94% unit learning curve, how many hours would be required to manufacture units 76-100? (Use the tables provided in the lesson). A) 507,683 B) 117,382 C) 507,717 D) 112,627Explanation / Answer
C) 507,717