Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Part 1 . Question 1. How many of the statements are true? (A) 0 (B) 1 (C) 2 (D)

ID: 344383 • Letter: P

Question

Part 1. Question 1. How many of the statements are true?

(A) 0   (B) 1   (C) 2   (D) 3     (E) 4

Statement 1. Scheduled receipts are the same as planned receipts

Statement 2. The IRF contains the product structure of the end-item

Statement 3. The POR is the inventory policy of the MRP

Statement 4. MRP minimizes cost

Part 2.   Questions 2-4

Consider the end-item weekly MRPs for May 1 with Qd missing in each MRP. Match the correct MRP with the proper lot size discipline.

MRP A

5-1

5-8

5-15

5-22

5-29

GR

75

112

61

36

SR

40

LT=2

PSB

247

212

100

39

8

SS=8

POR

5

Qd= ?

MRP B

GR

75

112

61

36

SR

40

LT=2

PSB

247

212

100

39

8

SS=8

POR

5

Qd= ?

MRP C

GR

75

112

61

36

SR

40

LT=2

PSB

247

212

100

39

9

SS=8

POR

6

Qd= ?

MRP D

GR

75

112

61

36

SR

40

LT=2

PSB

247

212

100

39

10

SS=8

POR

7

Qd= ?

Question 2. For Qd=3, which MRP is correct?

(A) MRP A     (B) MRP B     (C) MRP C     (D) MRP D     (E) none of the above

Question 3. For Qd=7+, which MRP is correct?

(A) MRP A     (B) MRP B     (C) MRP C     (D) MRP D     (E) none of the above

Question 4. For Qd=LFL, which MRP is correct?

(A) MRP A     (B) MRP B     (C) MRP C     (D) MRP D     (E) none of the above

Part 3.  

Question 5. Complete the end-item daily MRP for May 1.

MRP

5-1

5-2

5-3

5-4

5-5

GR

150

147

21

17

SR

60

LT=1

PSB

247

SS=16

POR

Qd= 5

How many statements are correct?     A. 0     B. 1     C. 2     D. 3     E. 4

Statement 1. The inventory on hand for May 2 is 157

Statement 2. The planned order release for May 3 is 10

Statement 3. The net requirements for May 4 is 17

Statement 4. The project stock balance for May 5 is 16

MRP A

5-1

5-8

5-15

5-22

5-29

GR

75

112

61

36

SR

40

LT=2

PSB

247

212

100

39

8

SS=8

POR

5

Qd= ?

MRP B

GR

75

112

61

36

SR

40

LT=2

PSB

247

212

100

39

8

SS=8

POR

5

Qd= ?

MRP C

GR

75

112

61

36

SR

40

LT=2

PSB

247

212

100

39

9

SS=8

POR

6

Qd= ?

MRP D

GR

75

112

61

36

SR

40

LT=2

PSB

247

212

100

39

10

SS=8

POR

7

Qd= ?

Explanation / Answer

Part 1: (B) 1

Statement 1. Scheduled receipts are the same as planned receipts - INCORRECT (scheduled receipts are given variables, not planned variables, whereas planned receipts are planned as a part of MRP)
Statement 2. The IRF contains the product structure of the end-item - INCORRECT (IRF is inventory records of items. It is the BOM which contains the product structure.)
Statement 3. The POR is the inventory policy of the MRP - CORRECT
Statement 4. MRP minimizes cost - INCORRECT (cost minimization is not an objective of MRP)

Part 2

Question 2. Qd will be 3 or its multiple. So, Qd=6 for MRP C is correct.
Question 3. Qd=7+ for MRP D only. So, MRP D is correct
Question 4. For Qd=LFL, MRP B is correct because, with Qd=5, the PSB at last day becomes exactly 8 (=SS). Otherwise, this would have been 3 which is less than SS.

Part 3

Statement 1. The inventory on hand for May 2 is 157 - CORRECT
Statement 2. The planned order release for May 3 is 10 - INCORRECT (it is 30)
Statement 3. The net requirements for May 4 is 17 - INCORRECT (it is 16+11=27)
Statement 4. The project stock balance for May 5 is 16 - INCORRECT (it is 17)

So, only one statement is correct.

MRP 1-May 2-May 3-May 4-May 5-May GR 150 147 21 17 SR 60 LT=1 PSB 247 157 10 -11 -28 SS=16 POR Qd= 5