Instruction: Write True if the statement is true, and write False if the statement is False on the space provided beside each question. Each question carries 5 points. 1 . Project planning exists throughout the project life. _ Tcwe - 2. Design/Bid/Build project delivery method is suitable for projects with well-defined project scope. Project estimate is usually done once in a project life cycle. Cost-capacity curves method of cost estimation is similar to square-foot estimating method used for projects in the building sector. 3. 4. d oetpury arangeune. 6. In Design/Bid/Build project delivery method, owner has higher control of the project during construction than in Design/Build project delivery method

Explanation / Answer

1- True. Planning of the project is done prior to commencement of the project and it remains through out the execution of the project.

2-True.When project scope is defined it is easy to design the project, bid for the project and building the project when successfully get the bid.

3- False. If the project is complicated and vague one, project estimation done more than once during the execution of the project.

4-False. Both have different aproach of estimation.

5-True. Both party should mutually agree.

6-True.