Match the terms with the definitions Actual Cost of Work Performed Budgeted Cost

ID: 347455 • Letter: M

Question

Match the terms with the definitions

Actual Cost of Work Performed

Budgeted Cost of Work Performed

Budgeted Cost at Completion

Cost Performance Index

Cost Variance

Estimated Cost at Completion

Schedule Performance Index

Schedule Variance

Budgeted Cost of Work Scheduled

Provides an indication of scheduling deviance in terms of dollars of work

Provides an indication of the status of the project in terms of cost

Ratio directly compares budgeted costs to actual costs based on work performed

Forecast of the total actual costs required to complete a project based on performance to date and estimates of future conditions

Indicates what the budgeted costs are for the work actually performed to date

Developed at the outset of the project and involves assigning to activities the amount budgeted for every activity

Ratio provides a direct relationship between work performed and work scheduled based on budgeted costs

Total costs actually incurred and recorded in accomplishing work performed during a given time period

Original cost estimate of the total cost of construction

      -       A.       B.       C.       D.       E.       F.       G.       H.       I.   

Actual Cost of Work Performed

      -       A.       B.       C.       D.       E.       F.       G.       H.       I.   

Budgeted Cost of Work Performed

      -       A.       B.       C.       D.       E.       F.       G.       H.       I.   

Budgeted Cost at Completion

      -       A.       B.       C.       D.       E.       F.       G.       H.       I.   

Cost Performance Index

      -       A.       B.       C.       D.       E.       F.       G.       H.       I.   

Cost Variance

      -       A.       B.       C.       D.       E.       F.       G.       H.       I.   

Estimated Cost at Completion

      -       A.       B.       C.       D.       E.       F.       G.       H.       I.   

Schedule Performance Index

      -       A.       B.       C.       D.       E.       F.       G.       H.       I.   

Schedule Variance

      -       A.       B.       C.       D.       E.       F.       G.       H.       I.   

Budgeted Cost of Work Scheduled

A.

Provides an indication of scheduling deviance in terms of dollars of work

B.

Provides an indication of the status of the project in terms of cost

C.

Ratio directly compares budgeted costs to actual costs based on work performed

D.

Forecast of the total actual costs required to complete a project based on performance to date and estimates of future conditions

E.

Indicates what the budgeted costs are for the work actually performed to date

F.

Developed at the outset of the project and involves assigning to activities the amount budgeted for every activity

G.

Ratio provides a direct relationship between work performed and work scheduled based on budgeted costs

H.

Total costs actually incurred and recorded in accomplishing work performed during a given time period

I.

Original cost estimate of the total cost of construction

Explanation / Answer

Actual Cost of Work Performed - H. Total costs actually incurred and recorded in accomplishing work performed during a given time period

Budgeted Cost of Work Performed - E. Indicates what the budgeted costs are for the work actually performed to date

Budgeted Cost at Completion - I. Original cost estimate of the total cost of construction

Cost Performance Index - C. Ratio directly compares budgeted costs to actual costs based on work performed

Cost Variance - B. Provides an indication of the status of the project in terms of cost

Estimated Cost at Completion - D.Forecast of the total actual costs required to complete a project based on performance to date and estimates of future conditions

Schedule Performance Index - G. Ratio provides a direct relationship between work performed and work scheduled based on budgeted costs

Schedule Variance - A. Provides an indication of scheduling deviance in terms of dollars of work

Budgeted Cost of Work Scheduled - F. Developed at the outset of the project and involves assigning to activities the amount budgeted for every activity