Problem 12-2 The following table lists the components needed to assemble an end
ID: 347624 • Letter: P
Question
Problem 12-2
The following table lists the components needed to assemble an end item, lead times, and quantities on hand.
a. If 20 units of the end item are to be assembled, how many additional units of E are needed? (Hint: You don't need to develop an MRP plan to determine this.)
Additional units
b. An order for the end item is scheduled to be shipped at the start of week 17. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don't need to develop an MRP plan for this part either.)
The latest week
Explanation / Answer
a) For 1 unit of End Item, the number of units of E required = BE+CE+DE = (2*2)+(1*2)+(3*2) = 12.
For 20 units of End item, the number of additional units of E required = (20*12) - 12 = 228 units
b) End item -> start of week 17 => start date = 17-2 = 15 weeks.
Item B, C and D ---> Max start week => 15-2 = 13 weks for all three.
Items E and F -> Max start week = 13-2 = 11 weeks
Items G and E -> Max start week = 13-1 = 12 weeks.
Items H and E -> Max start week = 13-2 = 11 weeks.
The order can be started maximum at 11th week.