A company's production facility, consisting of two identical machines, currently caters only to product A. The annual demand for the product is 4000 units. Management has now decided to introduce another product, B, which uses the same facilities as that of product A. Product B has an annual demand of 2000 units. In view of the uncertainties involved in producing two products, management desires to have an overall 10 percent capacity cushion. Given the following additional information, how many more machines are required? (Assume 8 hours/shift, 2 shifts/day, 250 days/year, and that no overtime is allowed) Processing Time Setup Time per Unit (in hours) per Batch Batch Size (in hours) Product (units) 2.0 2.8 100 200 16 No additional machines are necessary. One additional machine is necessary. Two additional machines are necessary. More than two additional machines are necessary.

Explanation / Answer

Time taken to meet demand of product A which is 4000 units

Cushion: 10%

Demand after including cushion: 4000*1.1: 4400

Batch size: 100 units

Processing time per unit: 2 hours

Processing time per batch: 200 hours

Setup time per batch: 8 hours

Total time per batch: 200 + 8 = 208 hours

No of batch to meet demand: 4400/100 = 44

Total time needed to meet demand of product A: 208*44 = 9152 hours

Time taken to meet demand of product B which is 2000 units

Cushion: 10%

Demand after including cushion: 2000*1.1: 2200 units

Batch size: 200 units

Processing time per unit: 2.8 hours

Processing time per batch: 560 hours

Setup time per batch: 16 hours

Total time per batch: 560 + 16 = 576 hours

No of batch to meet demand: 2200/200 = 11

Total time needed to meet demand of product A: 576*11 = 6336 hours

Total time needed to meet annual demand of product A and B: 9152 + 6336 = 15488 hours

Total time 1 machine works in 1 year: 8*2*250 = 4000 hours

So to meet the total demand company needs 4 machines which can complete work of 16000 hours which will be enough for annual demand with the required cushion