Milestone 6: Project Team Management
Several people working on the Recreation and Wellness Intranet Project are confused about their responsibilities for the testing portion of the project. Recall that the team members include you, a programmer/analyst and aspiring project manager; Patrick, a network specialist; Nancy, a business analyst; and Bonnie, another programmer/analyst. Mark Hudson is the project manager, and he has been working closely with managers in other departments to make sure everyone knows what’s going on with the project.
Prepare a RACI chart (using the template provided) to help clarify roles and responsibilities for these testing tasks. Document key assumptions you make in preparing the chart. Prepare the RACI chart based on the following information: The main tasks for testing include writing a test plan, unit testing, integration testing for each of the main system modules (registration, tracking, and incentives), system testing, and user acceptance testing. In addition to the project team members, a team of user representatives is available to help with testing, and Mark has also hired an outside consulting firm to help as needed.
Project Name RACI Chart Date Task Name 1 Name 2 Name 3 Name 4 R: Responsible A: Accountable C: Consulted I: InformedExplanation / Answer
Project Name RACI Chart Date Task Self - Programmer/Analyst Patrick- network Specialist Nancy - Business Analyst Bonnie - Programmer/Analyst Mark - Project Manager User Representatives Consultants' Writing a test plan I A R I C C Unit Testing R,A C I R,A Integration Testing C R,A I C I System Testing R A R R R I C User Acceptance Testing C I R C A R R: Responsible A: Accountable C: Consulted I: Informed