QUESTION 37 The estimated types and quantities of resources required for an acti
ID: 352658 • Letter: Q
Question
QUESTION 37 The estimated types and quantities of resources required for an activity together with the availability of ho 2 pol resources will influence the C a. project's acceptance criteria. 0 b. estimated duration for how long it will take to perform the activity. c. project scope document description d. actual costs of work performed. QUESTION 38 2 poin An assumption for a construction project could be O a. a grant will be secured to help fund the project. b. the materials to be used to construct the building. c, the regulations and codes required for the building the eivo of tha hraildino that ie to ha onnetrunted d Cick Save and Submit to save and submit Click Save All Answers to save all onswers Click Save an Sav Save All AnswersExplanation / Answer
37) option b, estimated duration for how long it will take to perform the activity.
the avilability of those resources and time required to procure those resources defines the duration for how long it takes to perform that activity. if it is easily available then it takes less time if not then it takes more time.
38) option a, A grant will be secured to help fund the project
if it is assumed that a grant is secured for the project, and for some reason it is not secured affects the project and its timeline. Hence a grant is an assumption.