I. True/False (2 Points each) Total 20 points 11. Because of its flexibility, project management is equally useful in ongoing, routine work as wel as unique, one-time projects. True False 12. One of the most significant driving forces behind the demand for project management is the ever increasing expansion of the product life cycle. True False ssary to have exactly the same strategic and operations criteria for different pr True False 14. several people working part-time on the same projects. rking on several projects at t he same time are more efficient than having Generally, people wo True FalseExplanation / Answer
11 False( as a project is not a routine and repetitive task, and is done only once. Project management cannot be used for routine activities which repeat daily normal routine).
12 False(since demand for project management increases due to shortened project life cycle).
13 False(Though mostly same criteria are used for different projects, it's not necessary that same criteria is used. It depends from to project and its necessity what criteria is used is determined).
14 False(as people working on several projects become less efficient due to switching concepts and work between projects)