Assume you are a software project Manager and that you have beenasked to compute

ID: 3607801 • Letter: A

Question

Assume you are a software project Manager and that you have beenasked to compute earned

value statistics for a small software project. The project has56 planned work tasks that are

estimated to require 582 persons-days to complete. At the timethat you have been asked to do

the earned value analysis. 5 tasks have been completed. Howeverthe project schedule indicates

that 8 tasks should have been completed. The following scheduledata (in person-days) are

Task                Plannedeffort                       Actual effort

1                              12                                       12

2                              15                                       11

3                              13                                       17

4                               8                                         9

5                               10                                       9

6                               18                                    -----

(Hint: SPI = BCWP / BCWS

SV=BCWP - BCWS

Person Complete = BCWP / BAC

BAC = ? (BCWSk) forall tasks k

Where BCWP = Budgeted Cost of WorkPerformed, BCWS = Budgeted Cost of Work

Scheduled, BAC = Budget atCompletion)

Explanation / Answer

Assume you are a software project Manager and that you have beenasked to compute