Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Can someone please help? I would like to check my formulas and answers. I have P

ID: 362395 • Letter: C

Question

Can someone please help? I would like to check my formulas and answers. I have Plan A as 168,000 and Plan B as 54,000. thank you

13.9

The S&OP team at Kansas Furniture, has received the following estimates of demand requirements:

July

Aug.

Sept.

Oct.

Nov.

Dec.

1,000

1,200

1,400

1,800

1,800

1,600

a)Assuming stockout costs for lost sales of $100 per unit, inventory carrying costs of $25 per unit per month, and zero beginning and ending inventory, evaluate these two plans on an incremental cost basis:

Plan A: Produce at a steady rate (equal to minimum requirements) of 1,000 units per month and subcontract additional units at a $60 per unit premium cost.

Plan B: Vary the workforce, to produce the prior month’s demand. The firm produced 1,300 units in June. The cost of hiring additional workers is $3,000 per 100 units produced. The cost of layoffs is $6,000 per 100 units cut back.

Note: Both hiring and layoff costs are incurred in the month of the change, (i.e. going from production of 1,300 in July to 1,000 in August requires a layoff (and related costs) of 300 units in August, just as going from production of 1,000 in August to 1,200 in September requires hiring (and related costs) of 200 units in September).

b)Which plan is best and why?

July

Aug.

Sept.

Oct.

Nov.

Dec.

1,000

1,200

1,400

1,800

1,800

1,600

Explanation / Answer

Plan A

Month

Demand

Production

End of period Inventory

Sub Contract Units

Inventory Cost

Subcontract Cost

June

1000

July

1000

1000

0

0

0

0

August

1200

1000

0

200

0

12000

September

1400

1000

0

400

0

24000

October

1800

1000

0

800

0

48000

November

1800

1000

0

800

0

48000

December

1600

1000

0

600

0

36000

Total Cost

$ 168000

Plan B

Month

Demand

Production

Hire

Layoff

Hire Cost

Layoff Cost

June

1300

July

1000

1000

0

300

0

18000

August

1200

1200

200

0

6000

0

September

1400

1400

200

0

6000

0

October

1800

1800

400

0

12000

0

November

1800

1800

0

0

0

0

December

1600

1600

0

200

0

12000

Total Cost

24000

30000

Total Cost in Plan B = 30000+24000 = $ 54000

b) Which plan is best and why?

Ans: In comparison to Plan A ,the better Plan is B due to total cost is less.

Plan A

Month

Demand

Production

End of period Inventory

Sub Contract Units

Inventory Cost

Subcontract Cost

June

1000

July

1000

1000

0

0

0

0

August

1200

1000

0

200

0

12000

September

1400

1000

0

400

0

24000

October

1800

1000

0

800

0

48000

November

1800

1000

0

800

0

48000

December

1600

1000

0

600

0

36000

Total Cost

$ 168000