Problem 6 Question Help Northcutt manufactures high-end racing bikes and is look

ID: 364356 • Letter: P

Question

Problem 6 Question Help Northcutt manufactures high-end racing bikes and is looking for a source of gear sprocket sets. Northcutt would need 1,250 sets a month. Supplier A is a domestic firm, and Suppliers B and C are located overseas. Cost information for the suppliers is as follows: Supplier A-Price of $150 per set, plus packing cost of $1.50 per set. Total inland freight costs for all 1,250 units would be $1,000 per month. Supplier B Price of $109 per set, plus packing cost of $2.00 per set. International transportation costs would total $4,000 per month, while total inland freight costs would be $650 per month Supplier C Price of $53 per set, plus packing cost of $1.50 per set. International transportation costs would total $5,100 per month, while total inland freight costs would be $700 per month. a. The total landed cost per unit for Supplier A is S(Enter your response rounded to two decimal places.)

Explanation / Answer

Problem 6

Total landed cost per unit for supplier A = $ 150+1.5+1000/1250

= 152.30

Problem 9)

X coordinator of weighted Center of gravity for the new firestation

= (2.5*172+4.5*52+1.5*200+2*38)/(172+52+200+38)

= (430+234+300+76)/462

= 1040/462

= 2.25