You have been asked to consult on setting up a LEAN production line for Baxter I
ID: 366464 • Letter: Y
Question
You have been asked to consult on setting up a LEAN production line for Baxter Industries, which produces injected plastic moldings for inkjet printers. Which of the following is NOT an element of Lean (Just-in-Time) manufacturing? O Having only the minimum quantities of required raw materials on site for the daily production run Rewarding workers for reducing production line set-up times. All of these are elements of Lean Using demand sensitive Push systems as much as possible. Focusing on improving how workers view quality so that only "zero defects" is acceptableExplanation / Answer
The answer should be
C. All of these are elements of Lean
Because all these expectations from the Lean system within the organization.