Consider the following proposed plan, for a different demand schedule, that comb

ID: 368317 • Letter: C

Question

Consider the following proposed plan, for a different demand schedule, that combines the strategy of hiring, layoffs, and utilizing overtime. Payroll costs are $6000 in wages per worker for regular time worked, with an overtime pay rate of $17 for each overtime hour. The cost of hiring a worker is $3400, and the cost of laying off a worker is $1900.

Quarter

Demand (hours)

Workforce

Hires

Layoffs

Overtime

(hours)

1

6,000

12

1

2

12,000

24

12

3

19,000

31

7

3,500

4

9,000

18

13

Total

85

20

13

3,500

The total cost for this plan would be $____ (Enter your response as an integer.)

Quarter

Demand (hours)

Workforce

Hires

Layoffs

Overtime

(hours)

1

6,000

12

1

2

12,000

24

12

3

19,000

31

7

3,500

4

9,000

18

13

Total

85

20

13

3,500

Explanation / Answer

Total cost for the plan will be calculated as :

Total cost for the plan

= Workforce strength x Payroll cost/ worker + Hiring cost / worker x Number of workers hired + Layoff cost /worker x Number of workers laid of + Overtime rate/ hour x Overtime hours

Therefore total cost of the plan

= 85 x 6000 + 20 x 3400 + 13 x 1900 + 17 x 3500

= $510,000 + $68,000 + $24,700 + $59,500

= $662,200

TOTAL COST FOR THIS PLAN WOULD BE = $662,200

TOTAL COST FOR THIS PLAN WOULD BE = $662,200