The folowing is a table of activities associated with a project at Rafay Ishfaqg
ID: 368705 • Letter: T
Question
The folowing is a table of activities associated with a project at Rafay Ishfaqg's scftware firm in Chicago, their durations, what activies each musi precede and the orash cost to reducs duration per week Activity Duration (weeks) Precedes Crash Cost/Week A (stant) B, C $120 F (and) Suppose that Relay is only given 7 woeks (instead of 10) to complete the project By how many wooks shoud each activity be crashed in order to moet the deadine? Assume that you can crash an woeks durebion Each Activity Should be Reduced BY Activity 3 woek[s) Enter your answer in the answer box and then click Check AnswerExplanation / Answer
There is another option:
Task Pre Duration ES EF Critical LS LF Slack A NA 2 0 2 yes 0 2 0 B A 2 2 4 3 5 1 C A 5 2 7 Yes 2 7 0 E B 2 4 6 5 7 1 F C,E 3 7 10 Yes 7 10 0