Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

46. Which of the following generally cannot be validated using a work breakdown

ID: 372305 • Letter: 4

Question

46. Which of the following generally cannot be validated using a work breakdown structure? a. Risk management b. Quality management c. Schedule control d. Cost Control e. All can be validated 47. Which of the following is not the level used to report status: a. Control account b. Work package c. Determined by the project manager d. Level 3 of the WBS e. All of the above 48. Almost all projects, because of their relatively short duration and often prioritized control resources require a. subsidiary planning b. execution planning c. detailed planning d. integrated planning e, any of the above 49. The scope baseline comprises which three elements? a. WBS, scope statement, and WBS dictionary b. WBS dictionary, charter, and requirements documentation e. Scope management plan, WBS, and WBS dictionary d. Scope statement, scope management plan, and WBS e· Charter, scope statement, and wBD 50. If a project team goes from three people to six, how many more communication channels are there? b. 6 c. 9 d. 12 e none of the above 51. Which of the following conflict handling modes do effective project managers use most often b. smoothing c. forcing d. confrontation e. levelling 52. On most projects, the majority of communications planning is done: b. c. d. e. during execution at the earliest stages of the project just prior to closeout evenly throughout each project phase during monitoring 53. In project management, overlapping phases may require additional resources to allow work to be done: a. in linear mode b. in tandem c. in sequence d. in angular mode e. in paralle

Explanation / Answer

46. Since, c) Schedule Control and d) Cost Control come under the primary scope of Work Breakdown Structure and b) Quality Management is related and secondary for WBS, they can be validated. However WBS focuses on end result but not on the process and hence a) Risk Management is the correct answer.

47. Since work package is the lowest level of WBS b) Work Package is the level not used to report status.

48. d) Integrated planning as it concerns several small projects of short duration

49. a) WBS, WBS dictionary and scope document are the elements of scope baseline.

50. With 3 people there are 3 channels and using combination formula for 6 people it will be 15 channels and hence d) 12 is answer

51.a)