Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

The following represents a project that should be scheduled using CPM: IMMEDIATE

ID: 376073 • Letter: T

Question

The following represents a project that should be scheduled using CPM: IMMEDIATE TIMES (DAYS) ACTIVITY PREDECESSORS a m b 2 1 1 3 4 11 1 3 11 2 3 11 F,G b. What is the critical path? O B-E-G-H OA-D-F-H OA-C-F-H O A-D-G-H c. What is the expected project completion time? (Round your answer to 3 decimal places.) Project completion time d. What is the probability of completing this project within 19 days? (Do not round intermediate calculations. Round your answer to 4 decimal places.) Probability days

Explanation / Answer

The expected duration as well as standard deviation of duration of each activity is presented below :

ACTIVITY

a

m

B

Expected duration

Standard deviation of duration

A

1

2

6

2.5

0.83

B

1

2

9

3

1.33

C

2

2

11

3.5

1.50

D

1

8

9

7

1.33

E

1

2

3

2

0.33

F

3

4

11

5

1.33

G

1

3

11

4

1.67

H

2

3

11

4.17

1.50

Following may be noted :

Expected duration of an activity = ( a + 4.m + b)/6

Standard deviation of activity = ( b – a) / 6

The Precedence diagram as follows :

                                                                                                       A

B

                          C

                                                                  D

E

                                                        F

                                               G

                                                                                                                H

The possible parallel paths and their corresponding expected durations as follows :

A-C-F-H = 2.5 + 3.5 + 5 + 4.17 = 15.17

A-D-F-H = 2.5 + 7 + 5 + 4.17 = 18.67

A-D-G-H = 2.5 +7 + 4 + 4.17 = 17.67

B-E-G-H = 3+ 2+ 4+ 4.17 = 13.17

               

Out of above , A-D-F-H has the longest duration and hence forms the critical path. Duration of the critical path is Project Completion time . Hence Project completion time will be 18.67 days

Variance of the duration of critical path

= Sum of Variances of activities A,D,F,H

= 0.83^2 + 1.33^2 + 1.33^2 + 1.5^2

= 0.6889 + 1.7689 + 1.7689 + 2.25

= 6.4767

Hence, standard deviation of the duration of critical path = square root ( 6.4767) = 2.544 days

Let Z value corresponding to probability that project will be complete within 19 days = Z1

Hence,

Expected project completion time ( i.e. expected duration of critical path) + Z1 x Standard deviation of duration of critical path = 19

Or, 18.67 + 2.544.Z1 = 19

Or, 2.544.Z1 = 19 – 18.67 = 0.33

Z1 = 0.33/2.544 = 0.1297 ( 0.13 rounded to 2 decimal places )

Probability corresponding to Z1 = 0.13 will be 0.55172

CRITICAL PATH = A-D-F-H

PROJECT COMPLETION TIME = 18.67 DAYS

PROBABILITY OF COMPLETING THE PROJECT WITHIN 19 DAYS = 0.55172

ACTIVITY

a

m

B

Expected duration

Standard deviation of duration

A

1

2

6

2.5

0.83

B

1

2

9

3

1.33

C

2

2

11

3.5

1.50

D

1

8

9

7

1.33

E

1

2

3

2

0.33

F

3

4

11

5

1.33

G

1

3

11

4

1.67

H

2

3

11

4.17

1.50